Our services is
turnkey I&C solutions
turnkey I&C solutions
Home / Projects
Projects
Finded: 314 projects
Project | Customer | Object of automation / Equipment |
Services | Work status |
---|---|---|---|---|
Kharta PP (Iraq) Units №2 and №3 (2 units per 200 MW) I&C and Water treatment I&C |
Siemens, Germany |
2 units per 200 MW (gas fired), WTP / S7, TXP-R |
Basic design, engineering, SPV of erection, commissioning, training | Detail engineering |
Syrdarinskaya PP (Uzbekistan), Demineralising plant I&C of unit №7, №8 Siemens, Germany |
DP |
S7 / PCS7 |
Basic design, engineering, commissioning | Finished |
Sredneuralskaya PP Unit №10 (300 MW) I&C |
Sverdlovenergo, Russia |
Unit 300 MW (gas, oil, coal fired) / TXP-R |
Basic design, engineering, delivery, SPV of erection and commissioning, support, training | Finished |
Krasnoyarskaya PP-1 Turbine №10 (55 MW) I&C |
Krasnoyarskaya PP-1, Russia |
Turbine 55 MW / TXP-R |
Basic design, engineering, delivery, SPV of erection, commissioning, support, training | Finished |
Mutnovskaya Geothermal PP Steam field I&C |
Kamchatskagro-promstroj, Russia |
Steam field / S7 |
Engineering, delivery, SPV of erection and commissioning, training | Finished |
Mutnovskaya Geothermal PP (2 units per 25 MW) I&C |
Siemens, Germany |
Power Plant / TXP-R |
Basic design, engineering, SPV of erection and commissioning, training | Finished |
Ivanovskaya PP Gas turbine (110 MW) I&C |
RAO UES, Russia |
Gas turbine 110 MW / TXP-R |
Basic design, engineering, delivery, SPV of erection, commissioning, training | Finished |
Kostolaz PP (Serbia and Montenegro) Unit №2 (100 MW) I&C |
Technoprom-export, Russia |
Unit 100 MW (coal fired) / TXP-R |
Engineering, delivery, SPV of erection and commissioning, training | Finished |
Pskovskaya PP Automated water quality monitoring for units №1 and №2 |
Pskovskaya PP, Russia |
WTP / PCS7 |
Engineering, delivery, SPV of erection, commissioning | Finished |
Krasnoyarskaya PP Boiler №6 (500 t/h) I&C |
Krasnoyarsk-energo, Russia |
Boiler 500 t/h (coal, oil fired) / TXP-R |
Basic design, engineering, delivery, SPV of erection, commissioning, support, training | Finished |
Zmijevskaya PP (Ukraine) Unit №8 (300 MW) I&C |
Siemens, Germany |
Unit 300 MW (coal, gas, oil fired) / TXP-R |
Engineering, SPV of erection and commissioning, training | Finished |
Suizhung PP (CPR) Unit №2 (800 MW) I&C |
Technoprom-export, Russia |
Unit 800 MW (coal fired) / TXP-R |
Engineering, delivery, SPV of erection and commissioning, support, training | Finished |
Suizhung PP (CPR) Unit №1 (800 MW) I&C |
Technoprom-export, Russia |
Unit 800 MW (coal fired) / TXP-R |
Engineering, delivery, SPV of erection and commissioning, support, training | Finished |
Konakovskaya PP Water treatment I&C |
Konakovskaya PP, Russia |
WTP / S7 |
Basic design, engineering, delivery, SPV of erection, commissioning, training | Finished |
Novgorodskaya PP Boiler №2 (420t/h) I&C |
Novgorodenergo, Russia |
Boiler 429 t/h (coal, gas fired) / TXP-R |
Basic design, engineering, SPV of erection, commissioning, training | Finished |
Nizhnekamskaya PP Water treatment I&C |
Nizhnekamskaya TPP, Russia |
WTP / S7 |
Basic design, engineering, delivery, SPV of erection, commissioning, training | Finished |
Orskaya PP Turbine №11 (65 MW) I&C |
Orskaya TPP, Russia |
Turbine 65 MW / TXP-R |
Basic design, engineering, delivery, SPV of erection, commissioning, training | Finished |
Sredneuralskaya PP Gas turbodetander (12 MW) I&C |
Sverdlovenergo, Russia | Gas turbodetander 12 MW | Basic design, engineering, SPV of erection, commissioning, training | Finished |
Pervouralskaya PP Heating boiler (420 t/h) I&C |
Sverdlovenergo, Russia | Boiler 420 t/h (gas, oil fired) | Basic design, engineering, SPV of erection, commissioning, training | Finished |
St.Petersburg Nort-West CCPP Unit №2 (450 MW) I&C |
Siemens, Germany | Combined circle unit 450 MW | AS engineering, participation in SPV of erection and commissioning, training | Finished |
© 1993-2024 Intermatic AG
Leninskaya Sloboda st. 21, building 1, Moscow, 115280, Russia
+7 (495) 108 11 82 e-mail: office@intermatic.energy
+7 (495) 108 11 82 e-mail: office@intermatic.energy